EGAT Baseload Power Projects

section-head-development-project

     According to PDP 2018, there is the necessity to develop power plants to secure the power system and meet the growing demand from 2018-2037 as follows:

  

Scheduled
commercial
operation
date (SCOD)
Power Plant Province Fuel Capacity
(MW)
2020 - Replacement of Bang Pakong Power Plant Units 1-2

 

Chachoengsao Natural gas 1,450
2025 - Replacement of Nam Phong Power Plant 


Khon Kaen


Natural gas


650


2026

- South Bangkok Power Plant (Addition)

- Replacement of Mae Moh Power Plant Units 8-9

 

Samut Prakan

Lampang

Natural gas

Coal

700

600

2027

-  South Bangkok Power Plant (Addition)

- Surat Thani Power Plant Block 1

Samut Prakan

Surat Thani

Natural gas

Natural gas

1,400

700

2028 - North Bangkok Power Plant (Addition) Nonthaburi Natural gas 700
2029 - Surat Thani Power Plant Block 2 Surat Thani Natural gas 700
2035 - North Bangkok Power Plant (Addition) Nonthaburi Natural gas 700