EGAT's Power Projects

section-head-development-project

     The official power development plan (PDP) 2015 was approved by the Cabinet on June 30, 2015. According to PDP 2015, there is the necessity to develop power plants to secure the power system and meet the growing demand in Southern provinces and metropolitan areas from 2019-2025 as follows:

Scheduled
commercial
operation
date (SCOD)
Power Plant Province Fuel Capacity
(MW)
2018 - Replacement of Mae Moh Power Plant units 4-7

 

Lampang Coal 655
2019

- Replacement of Bang Pakong Power Plant Units 1-2


- Replacement of South Bangkok Power Plant Units 1-5


- Replacement of Wangnoi Power Plant Blocks 1-2


- Krabi Power Plant

 

Chachoengsao

Samut Prakan

Ayutthaya

Krabi
Natural gas

Natural gas

Natural gas

Coal
1,300

1,350

1,470

800
2021 - Thepa Power Plant Unit 1

 

Songkla Coal 1,000
2022 - Replacement of South Bangkok Power Plant Blocks 1-2

 

Samut Prakan Natural gas 1,470