EGAT’s new power plant development projects according to the Power Development Plan 2018-2037, Revision 1 (PDP2018 Rev.1) are as follows:

1. Thermal Power Plants

EGAT has developed thermal power plants in accordance with PDP2018 Rev.1 since 2018. The projects approved by the Cabinet and in the approval process are as follows:

1.1 Approved Projects

ProjectContracted Capacity
(MW)
Scheduled Commercial Operation DateFuel
Mae Moh Power Plant Replacement
Project, Units 8-9
(Mae Moh Thermal Power Plant Project,
Unit 15)
6002026Lignite
Total Capacity600

Remark: The project was approved by the Cabinet on May 24, 2022.

1.2 Projects Requesting Approval from the Cabinet

ProjectContracted Capacity
(MW)
Scheduled Commercial Operation DateFuel
Nam Phong Power Plant Replacement Project
(Nam Phong Combined Cycle Power Plant,
Block 3)
6502025Natural Gas
South Bangkok Power Plant Project (Addition)
(South Bangkok Combined Cycle Power Plant Project, Blocks 5-7)
700 (Block 5)
1,400 (Blocks 6-7)
2026
2027
Natural Gas
Surat Thani Power Plant Project, Blocks 1-2
(Phunphin Combined Cycle Power Plant Project,
Blocks 1-2)
700 (Block 1)
700 (Block 2)
2027
2029
Natural Gas
North Bangkok Power Plant Project (Addition)
(North Bangkok Combined Cycle Power Plant
Project, Block 3)
7002028Natural Gas
Total Capacity4,850

2. Hydropower Plants Downstream of Irrigation Dams

EGAT has developed hydropower plants downstream of irrigation dams with Royal Irrigation Department since 2007. Ten projects have been completed and are in commercial operation. On June 18, 2024, the Cabinet approved the construction of the following four projects:

ProjectProvinceContracted Capacity
(MW)
Estimated Completion Date
Lamtakong Dam Hydropower PlantNakhon Ratchasima1.502025
Lam Pao Dam Hydropower PlantKalasin2.502025
Huay Mae Tho Dam Hydropower PlantTak1.252026
Krasiew Dam Hydropower PlantSuphan Buri1.502026
Total Capacity6.75

3. Renewable Power Plants

A key project in 2024 was the 24 MW Hydro-Floating Solar Hybrid at Ubol Ratana Dam, Khon Kaen Province operated with the Energy Management System (EMS) and Battery Energy Storage System (BESS) to enhance continuous and efficient electricity generation. The Cabinet approved the project on March 14, 2023. It started the commercial operation on March 5, 2024.

EGAT plans to implement additional floating solar projects with a total capacity of 2,656 MW, which have been approved by EGAT Board of Directors and are in approval process of the Cabinet as follows:

3.1 Floating Solar Projects in the Approval Process of the Cabinet

ProjectContracted Capacity
(MW)
Scheduled Commercial Operation Date
Bhumibol Dam Floating Solar Project 11582026
Srinagarind Dam Floating Solar Project 11402026
Vajiralongkorn Dam Floating Solar Project 1502027
Total Capacity348

3.2 Floating Solar Projects Approved by EGAT Board of Directors

ProjectContracted Capacity
(MW)
Bhumibol Dam Floating Solar Project 2300
Bhumibol Dam Floating Solar Project 3320
Srinagarind Dam Floating Solar Project 250
Srinagarind Dam Floating Solar Project 3280
Srinagarind Dam Floating Solar Project 4300
Vajiralongkorn Dam Floating Solar Project 240
Ubol Ratana Dam Floating Solar Project 260
Ubol Ratana Dam Floating Solar Project 3200
Ubol Ratana Dam Floating Solar Project 4280
Nam Phung Dam Floating Solar Project30
Sirindhorn Dam Floating Solar Project 2200
Sirindhorn Dam Floating Solar Project 3248
Total Capacity2,308

3.3 Mae Moh Solar Farm Project, Phase 1, Lampang Province

The objective of Mae Moh Solar Farm Project with a contracted capacity of 38.5 MW is to reduce the use of power supplied from the transmission system of Mae Moh Mine, increase the proportion of renewable energy in EGAT’s electricity generation, and support Carbon Neutrality policy. The project is not intended for commercial purposes. It is scheduled to supply electricity to Mae Moh mining system by the end of 2025.