Khlong Tron small Hydropower Plant

(Uttaradit Province)

Background

Khlong Tron Dam is constructed for the purpose of irrigation. The construction of the dam was completed in 1998. Water discharged from the reservoir into the Khlong Tron is stored by the Khlong Tron weir located at downstream far from the reservoir about 17 kilometers. The water is supplied to lower planting areas in Nam Pad and Thong Saen Khan Districts in Uttaradit Province for the maximum benefit.

Characteristics of Dam

Type
Earthfill dam with clay core
Reservoir storage capacity
53 m3
Catchment area
265 m2
Crest Level
198.50 MSL
Length
220 m
Height
48 m

Characteristics of Power Plant

Structure
Reinforced concrete
2.50 MW
Average annual generated electricity
11.83 million kWh

Contact

Skip to content