Transmission System Construction and Renovation Projects
Important Transmission System Projects/Plans That Have Been Approved and are under Implementation
Project
Expected Year of Completion
Transmission System Renovation Plan for Power Purchase from SPP Firm Cogeneration with Contract Period Ending by 2019-2025 (TSFC)
2024*
Transmission System for Hydro-Floating Solar Hybrid Project of Ubol Ratana Dam (URS1)
2024*
Transmission System Renovation and Expansion Project, Phase 1: Substation (RSP1)
2025
Transmission System Renovation and Expansion Project, Phase 1: Transmission Line (RLP1)
2025
Main Transmission System Expansion Project for Power Purchase from SPP Cogeneration Power Plants Based on Request for Proposal 2010 (SPPC)
2025
Transmission System Development Project for Power Purchase from Independent Power Producers (IPPP)
2026
Transmission System Development for Power Purchase from Small Power Producers, Phase 1 (SPP1)
2026
Transmission System Renovation and Expansion Project, Phase 2 (RTS2)
2027
Transmission System Improvement Project in Upper Northern Region to Enhance System Security (TIPN)
2027
Transmission System Expansion Project, Phase 12 (TS12)
2027
Bulk Power Supply for the Greater Bangkok Area, Phase 3 (GBA3)
2028
Transmission System Improvement Project in Eastern Region to Enhance System Security (TIPE)
2028
Transmission System Improvement Project in the Western and Southern Regions to Enhance System Security (TIWS)
2028
Submarine Cable Development Project to Koh Samui District in Surat Thani Province to Enhance System Security (SPSS)
2029
Substation Improvement Plan for System Connection in Compliance with EGAT’s Connection Code (SICC)
2029
Transmission System Improvement Project in the Northeast, Lower North, and Central Region including Bangkok to Enhance System Security (TIEC)
2031
Transmission System Improvement Project in Lower Southern Region to Enhance System Security (TILS)
2032
Remark: Construction was completed in 2024.
Important Transmission System Projects/Plans to Be Proposed for Approval in the Future
Project
Expected Year of Completion
Transmission System for Floating Solar Projects of EGAT Dams
2027 onward
Transmission System for North Bangkok Power Plant (Additional) Project, Phase 1 (NBA1)
2027
Transmission System for South Bangkok Power Plant (Additional) Project (SBA1)
2028
Transmission System Improvement Project to Accommodate the Renewable Power Purchase (TIRP)
2028
Transmission System Development for Special Economic Zone Project, Phase 1 (SEZ1)
2028
Transmission System Development in the Area of Loei, Nong Bua Lam Phu, and Khon Kaen Provinces for Power Purchase from Lao PDR Projects, Phase 2 (LNK2)
2030
Transmission System Development in the Area of Nan, Phrae, and Uttaradit Provinces for Power Purchase from Lao PDR Projects (NPUP)
2031
Bulk Power Supply for the Greater Bangkok Area, Phase 4 (GBA4)
2031
Transmission System Renovation and Expansion Project, Phase 3 (RTS3)
2031
Transmission System Renovation and Expansion Project, Phase 4 (RTS4)
This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics".
cookielawinfo-checbox-functional
11 months
The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional".
cookielawinfo-checbox-others
11 months
This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other.
cookielawinfo-checkbox-necessary
11 months
This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary".
cookielawinfo-checkbox-performance
11 months
This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance".
viewed_cookie_policy
11 months
The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data.