KARN@EGAT
Executive Officers
updated 15 Jan. 2025
KARN@EGAT
7 July 2021Transmission System Construction and Renovation Projects
1. Bulk Power Supply for the Greater Bangkok Area Project, Phase 2 (GBAS2) Being a successive project of Phase 1, the investment cost of GBAS2 is 9,170 million Baht consisting of the construction of transmission lines of 88.80 circuit-kilometers and a new substation, expansion of 4 substations, installation of transformers of 5,200 MVA and capacitor […]